exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 1250 discussion

Actual exam question from PMI's PMP
Question #: 1250
Topic #: 1
[All PMP Questions]

A human resources (HR) cost report was disclosed, by error, to all members of the project team. This situation generated a conflict between the team members about differences in their salaries.

What should the project manager have done to avoid this situation?

  • A. Ensured reports with significant information were not included in the communications management plan
  • B. Included noncompliance punishment measures in the communications management plan
  • C. Defined the appropriate recipients for the report in the communications management plan
  • D. Validated the information and the appropriate recipients per the communications management plan
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
arthigaf
1 month ago
Selected Answer: C
C is correct answer
upvoted 1 times
...
Jordarlu
3 months, 2 weeks ago
Selected Answer: C
the project manager wouldn't typically have control over emails sent by the HR department. I will vote for C
upvoted 1 times
...
victory108
8 months, 1 week ago
Selected Answer: D
D. Validated the information and the appropriate recipients per the communications management plan
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...