Question #: 378
Topic #: 1
[All CAPM Questions]

An adaptive project manager is migrating the company's new website. The project manager must work with the team to invest full capacity on this project because it is the company's top-ranked project in the portfolio. In order to increase throughput and provide consistent delivery, the project manager needs to assign members who are currently involved with other projects.

How should the project manager assign the team members to this project?

  • A. Full allocation
  • B. Task switching
  • C. Prediction
  • D. Multitasking
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
JesseChou_123
1 month, 1 week ago
Selected Answer: A
In adaptive (Agile) project management, maximizing focus and throughput is essential. When the project is the top-ranked initiative in the portfolio, the best way to ensure consistent and high-quality delivery is by assigning team members with full allocation to that project.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...