Question #: 387
Topic #: 1
[All CAPM Questions]

A project team member is discussing a new project with their manager. The project is very similar to a project that was delivered last year and the scope is very well documented.

Which of the following project delivery approaches should be recommended?

  • A. Adaptive
  • B. Traditional
  • C. Extreme
  • D. Hybrid
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
JesseChou_123
1 month, 1 week ago
Selected Answer: B
When a project: Has a well-defined and stable scope, Is similar to past projects, and Has clear documentation and requirements, …the Traditional (also called Predictive or Waterfall) approach is the most appropriate. This method works best when: Requirements are unlikely to change, The work is straightforward and repeatable, and A sequential process is effective (e.g., planning → execution → delivery).
upvoted 1 times
...
Jtic
8 months ago
Selected Answer: B
Correct
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...