exam questions

Exam CAPM All Questions

View all questions & answers for the CAPM exam

Exam CAPM topic 1 question 388 discussion

Actual exam question from PMI's CAPM
Question #: 388
Topic #: 1
[All CAPM Questions]

A project is composed of three phases that are implemented in parallel without affecting one another. The baselines for each individual phase have been approved by the major stakeholders, and there is a minimal ability to vary the baselines during the execution of the project.

Which methodology did the project manager adopt?

  • A. Iterative approach
  • B. Predictive approach
  • C. Incremental approach
  • D. Hybrid approach
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
JesseChou_123
1 month, 1 week ago
Selected Answer: B
In the scenario described: The three phases are executed in parallel (which is allowed in predictive approaches), Each has an approved baseline, and There is little ability to vary these during execution — all hallmarks of a predictive methodology.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...