A project manager is leading a project that will be delivered using a Scrum framework. The organization has an innovative project management office (PMO) that fully supports agile and also has a very friendly procurement team. A new vendor needs to be engaged to provide more developers for a new reporting platform.

What should the project manager do?

  • A. Consult the development team and engage a vendor that is recommended by them.
  • B. Use a formal approach using procurement policies, procedures, forms, and work instructions.
  • C. Consult the product owner and engage a vendor that is recommended by them.
  • D. Use an agile approach and engage a vendor that delivered well in a previous organization.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Okstm
6 months, 1 week ago
Selected Answer: B
While Scrum and agile practices emphasize flexibility and adaptability, procurement—especially when involving third-party vendors—still requires adherence to formal procedures to ensure that the engagement is legitimate, compliant, and in line with organizational and legal requirements.
upvoted 2 times
...
victory108
8 months, 1 week ago
Selected Answer: B
B. Use a formal approach using procurement policies, procedures, forms, and work instructions
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...