A defect is identified during user acceptance testing that could significantly impact the system's performance. The project team has advised that this defect puts the delivery date at risk.
Which risk management process should be performed?
A.
Perform Qualitative Risk Analysis, to assess the extent of the system performance impact
B.
Monitor Risks, to install system performance monitoring tools and update the risk register
C.
Plan Risk Responses, to outline the possible options to bypass the system performance issue
D.
Perform Quantitative Risk Analysis, to outline the details of the system performance issues
When a defect is identified that significantly impacts system performance and puts the delivery date at risk, it is crucial to develop a plan to address the issue. Planning risk responses involves identifying and evaluating potential options to mitigate or bypass the performance issue, ensuring that the project can continue to progress and meet its deadlines. This proactive step helps to manage the risk effectively and minimize its impact on the project's success.
Tricky one answer is B. Monitor Risks, to install system performance monitoring tools and update the risk register
upvoted 2 times
...
...
This section is not available anymore. Please use the main Exam Page.PMP Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
sblivia
1 month ago8af5887
5 months, 1 week agoSarvesh_D
6 months, 1 week agoAmirov
6 months, 1 week agovictory108
7 months agovictory108
5 months ago