A lead project manager for an agile project needs to prioritize requirements, define the scope of the initial product, and deliver the approved scope in a series of multiple versions. What should the project manager do next?
A.
Determine the expected benefits of each requirement to maximize the overall business value.
B.
Ask the lead developer to run a meeting with the stakeholders to agree on an ordered list.
C.
Work with the product owner to evaluate and prioritize the requirements.
D.
Prioritize the requirements based on the hierarchical level of the requesting stakeholders.
The product owner plays a crucial role in agile projects by representing the stakeholders and ensuring that the team is working on the most valuable features. By collaborating with the product owner, the project manager can effectively evaluate and prioritize the requirements based on their value, feasibility, and alignment with the project's goals. This approach ensures that the initial product scope is well-defined and that the team can deliver the approved scope in a series of multiple versions.
C. Work with the product owner to evaluate and prioritize the requirements
upvoted 1 times
...
This section is not available anymore. Please use the main Exam Page.PMP Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.