During the setup of an agile project, the product owner expressed clear interest in having features released during product development over having the product completed in one year. What should the project manager do?
A.
Facilitate sprint planning sessions with a focus on defining the minimum viable product (MVP).
B.
Design a set of metrics including velocity, which is a good measure of value delivered.
C.
Promote a productive environment where everybody can work without interruptions from the rest of the team members.
D.
Create a reward system recognizing group contributions to get people motivated and improve performance.
By focusing on the MVP, the project manager ensures that the most valuable features are delivered early and continuously throughout the product development process. This aligns with the product owner's interest in having features released incrementally, allowing for early feedback and adjustments. Facilitating sprint planning sessions with this focus helps the team prioritize work effectively and maintain a clear direction towards delivering valuable features.
A. Facilitate sprint planning sessions with a focus on defining the minimum viable product (MVP)
upvoted 1 times
...
This section is not available anymore. Please use the main Exam Page.PMP Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
sblivia
1 month agovictory108
7 months ago