Question #: 1400
Topic #: 1
[All PMP Questions]

An agile project team is working on an infrastructure product to be delivered incrementally over several iterations. Midway through the third iteration, the whole company is informed that the operating systems supported by the infrastructure will be terminated in the upcoming quarter. Several thousand machines will be impacted by this change.

What should the project manager do first?

  • A. Add product backlog items to prioritize operating system stories.
  • B. Inform the product owner and request more project resources.
  • C. Prioritize the upgrade of project machines with the IT department.
  • D. Schedule a session with stakeholders to understand the impact.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
NK1988
4 months, 2 weeks ago
Selected Answer: D
When a significant change impacts the project, the project manager's first step should be to assess the situation by engaging with stakeholders to understand the full scope and implications of the change. This includes evaluating how the operating system termination will affect the project, its deliverables, and any dependencies.
upvoted 1 times
...
MonBouj
7 months ago
Selected Answer: D
D. Schedule a session with stakeholders to understand the impact. By scheduling a session with stakeholders, the project manager can effectively assess the situation, understand the implications of the operating system termination, and make informed decisions about how to proceed with the project. This collaborative approach enhances communication and ensures that the team can adapt their plans to meet the new requirements.
upvoted 2 times
...
victory108
7 months ago
Selected Answer: D
D. Schedule a session with stakeholders to understand the impact
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago