When executing a project, a recently hired subject matter expert (SME) who reviewed the execution progress remarked that the schedule could be crashed and that the schedule was not assessed properly. What should the project manager do next?
Why Not the Other Options?
A. Update the schedule baseline – Premature. You must assess the current baseline first before making any updates.
B. Update the risk register – May be needed later if schedule crashing introduces risks, but not the first step.
D. Initiate a change request – Also comes after reviewing and confirming that a change is warranted.
This section is not available anymore. Please use the main Exam Page.CAPM Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
JesseChou_123
1 month, 1 week agoJtic
8 months ago