A project has encountered some difficulties that will impact the project management plan and the project management process. Which two actions should the project manager take? (Choose two.)

  • A. Perform quality management.
  • B. Submit a change request.
  • C. Perform a risk analysis.
  • D. Perform integrated change control.
  • E. Perform integrated project management.
Show Suggested Answer Hide Answer
Suggested Answer: BD 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
JesseChou_123
1 month ago
Selected Answer: BD
When difficulties impact the project management plan or processes, the project manager needs to formally submit a change request to document and propose adjustments. Then, the project manager must perform integrated change control to review, approve, or reject the change request and update project documents accordingly.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...