exam questions

Exam PgMP All Questions

View all questions & answers for the PgMP exam

Exam PgMP topic 1 question 55 discussion

Actual exam question from PMI's PgMP
Question #: 55
Topic #: 1
[All PgMP Questions]

Which of the following statements is most accurate about the critical path?

  • A. The critical path is always one path that shows the project duration.
  • B. The critical path has no float.
  • C. The critical path is the longest path because it has the most activities.
  • D. The critical path reveals which path has the most risk of failure.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Nugi
4 months, 2 weeks ago
Selected Answer: B
Critical Path is the longest sequence of activities in a project schedule that determines the shortest possible time to complete the project. Float (or Slack) is the amount of time an activity can be delayed without delaying the project's overall completion date.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago