Exam PfMP topic 1 question 141 discussion

Actual exam question from PMI's PfMP
Question #: 141
Topic #: 1
[All PfMP Questions]

Which action should a portfolio manager take first after a significant change in organizational strategy?

  • A. Perform a capability and capacity analysis.
  • B. Organize a portfolio review meeting.
  • C. Interview senior executive stakeholders.
  • D. Rebalance the portfolio components.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
tpkhoa
3 months ago
Selected Answer: C
IMO, should be interview executer manager to understand new strategy first.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel