exam questions

Exam PMI-RMP All Questions

View all questions & answers for the PMI-RMP exam

Exam PMI-RMP topic 1 question 439 discussion

Actual exam question from PMI's PMI-RMP
Question #: 439
Topic #: 1
[All PMI-RMP Questions]

A risk manager is collaborating with project stakeholders and the project team to identify risks in a construction project. The risk manager intends to use an approach that engages stakeholders based on information, such as scope baseline and project estimates, while also determining risk impacts based on this approach.

Which risk identification approach should the risk manager use to achieve this goal?

  • A. Delphi technique
  • B. Strengths, weaknesses, opportunities, and threats (SWOT) analysis
  • C. Assumptions and constraints analysis
  • D. Brainstorming technique
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
NordSee
3 months, 1 week ago
Selected Answer: D
question, wouldn't it be Brainstorming? Maybe, I'm lacking knowledge but still I'm not ye having enough confident why A is correct... Can someone help my understanding?
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago