exam questions

Exam PfMP All Questions

View all questions & answers for the PfMP exam

Exam PfMP topic 1 question 184 discussion

Actual exam question from PMI's PfMP
Question #: 184
Topic #: 1
[All PfMP Questions]

An input to the process to optimize the portfolio is:

  • A. portfolio process assets.
  • B. the portfolio charter.
  • C. capability and capacity analysis.
  • D. quantitative and qualitative analysis.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
tpkhoa
3 months ago
Selected Answer: C
The process of optimizing a portfolio focuses on aligning portfolio components with strategic objectives while ensuring efficient use of resources. To do this effectively, capability and capacity analysis is a crucial input
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago