In managing portfolio risks, which document is most useful to communicate a newly identified risk to stakeholders?

  • A. Portfolio report
  • B. Status report
  • C. Risk register
  • D. Risk component chart
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
tpkhoa
3 months ago
Selected Answer: C
The risk register is the primary document used to record, track, and communicate portfolio risks. When a new risk is identified, it is documented in the risk register along with: • Risk description • Probability and impact assessment • Potential response strategies • Risk owner and mitigation plans The risk register is shared with stakeholders to ensure transparency and proactive risk management.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago