Exam PfMP topic 1 question 230 discussion

Actual exam question from PMI's PfMP
Question #: 230
Topic #: 1
[All PfMP Questions]

The portfolio performance management plan should include:

  • A. portfolio goals and strategies, performance measurement tactics, and the portfolio governance model.
  • B. anticipated benefit realization, target dates, and the earned value of components.
  • C. resource utilization, resource gaps, and performance metrics.
  • D. performance roles and responsibilities, metrics, and the reporting process.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
tpkhoa
3 months ago
Selected Answer: A
The Portfolio Performance Management Plan defines how performance will be measured and managed across the portfolio.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago