The portfolio manager has obtained a prioritized inventory of work for each of the subportfolios of new products, regulatory, and quality improvement. Each subportfolio has been prioritized based on the objectives contained in the subportfolio charters. The executive sponsor has requested that the portfolio manager identify a best-practice approach to incorporate the subportfolio’s prioritization into an overall portfolio prioritization.
The portfolio manager has determined that this approach should develop a process to:

  • A. implement a portfolio multi-criteria weighted ranking.
  • B. evaluate capability and capacity.
  • C. integrate the subportfolios into the portfolio management plan.
  • D. utilize graphical and analytical methods.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
tpkhoa
3 months ago
Selected Answer: A
Should be A when combine multi-pf
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel