Exam PfMP topic 1 question 128 discussion

Actual exam question from PMI's PfMP
Question #: 128
Topic #: 1
[All PfMP Questions]

A portfolio manager is approached by a key stakeholder of a large portfolio. In order to achieve the organization’s strategy and objectives, the stakeholder requests a high-level plan that shows the portfolio’s internal and external dependencies.
The portfolio manager should provide the key stakeholder with a portfolio:

  • A. strategic plan that contains the portfolio schedule.
  • B. charter that contains a detailed portfolio timeline.
  • C. roadmap that contains component timelines.
  • D. dependency map that contains associated strategic objectives.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Currently there are no comments in this discussion, be the first to comment!
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...