Exam PgMP topic 1 question 86 discussion

Actual exam question from PMI's PgMP
Question #: 86
Topic #: 1
[All PgMP Questions]

You are the program manager for your organization. Your current program, which has just been initiated, needs to launch several projects in order to create all of the benefits of the program. What document do you need to create in order to initiate the projects within your program?

  • A. Project charter
  • B. Program charter
  • C. Program scope statement
  • D. Project preliminary scope statement
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
f07e1dd
2 weeks, 6 days ago
Selected Answer: B
I need a Program Charter to initiate the projects. Then the project manager will develop the project charter for the program manager. In other words a program manager cannot initiate any projects until authorized by a program charter.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...