Question #: 294
Topic #: 1
[All PgMP Questions]

A program experiences issues during execution. The stakeholders are concerned and the program manager feels pressure to act on these issues.
What tool should be used to trigger a planned response when receiving lower than expected results?

  • A. Key performance indicators
  • B. Benefits management plan
  • C. Communications management plan
  • D. Ishikawa diagram
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Currently there are no comments in this discussion, be the first to comment!
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...