Actual exam question from PMI's PMI-RMP
Question #: 51
Topic #: 1
[All PMI-RMP Questions]

During the initial risk planning process, the risk manager and project manager discuss ways to handle known risks. Which project reserve should the project manager use to budget for known risks?

  • A. Budget reserve
  • B. Contingency reserve
  • C. Change management reserve
  • D. Risk reserve
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Currently there are no comments in this discussion, be the first to comment!
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...