While creating the appropriate risk strategy, the project manager discovers that the project team lacks the necessary expertise to define the risk management plan. What additional resources should be utilized?

  • A. Consultants, organizational process assets, subject matter experts, and stakeholder tolerance analysis
  • B. Consultants, industry group, and subject matter experts
  • C. Consultants, professional and technical associations, subject matter experts, and industry groups
  • D. Consultants, professional and technical associations, and subject matter experts
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
c9619c8
1 month ago
Selected Answer: C
Consultants, professional and technical associations, subject matter experts, and industry groups is the best answer
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago