exam questions

Exam PMI-RMP All Questions

View all questions & answers for the PMI-RMP exam

Exam PMI-RMP topic 1 question 125 discussion

Actual exam question from PMI's PMI-RMP
Question #: 125
Topic #: 1
[All PMI-RMP Questions]

The risk manager of a medium-sized project is performing risk response planning with the project team. The proposed action for one specific, primary risk introduces a secondary risk.
What should the risk manager and the risk owner of the primary risk do about this situation?

  • A. Take no action, as secondary risks are not important for the successful execution of a project.
  • B. Inform the project manager about the occurrence of a secondary risk and propose to increase the management reserve.
  • C. Perform an analysis to calculate the estimated required budget for the secondary risk and propose to increase the management reserve accordingly.
  • D. Produce an agreed risk description, assess the probability, impacts, and select an appropriate response strategy for the secondary risk
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Currently there are no comments in this discussion, be the first to comment!
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...