A system enhancement project has been initiated to address the concerns of an external group of stakeholders not included in the first release. What should be done to ensure stakeholder satisfaction with the enhancement?
A.
Provide all sign-off project documentation to the stakeholders for information purposes only.
B.
Solicit feedback and add requirements to the project backlog.
C.
Request that the project manager identify all affected project stakeholders.
D.
Engage all stakeholders early in the requirements gathering phase to define acceptance criteria.
Currently there are no comments in this discussion, be the first to comment!
This section is not available anymore. Please use the main Exam Page.PMI-PBA Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Comments