exam questions

Exam PMI-SP All Questions

View all questions & answers for the PMI-SP exam

Exam PMI-SP topic 1 question 33 discussion

Actual exam question from PMI's PMI-SP
Question #: 33
Topic #: 1
[All PMI-SP Questions]

SIMULATION -
Fill in the blank with the appropriate word. When activities are logically linked, they become the __________

Show Suggested Answer Hide Answer
Suggested Answer: Schedule
An activity is an individual element of work that is logically linked to other activities to form the schedule. Its primary characteristics include an overall duration based upon the resources applied to it (manpower, material, and equipment), as well as a start and completion date that is tied to a work calendar. It also has a relationship with other activities (predecessors and successors).

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Currently there are no comments in this discussion, be the first to comment!
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...