Which of the following are the inputs to the Develop Project Charter process? Each correct answer represents a complete solution. Choose all that apply.

  • A. Procurement document
  • B. Contract
  • C. Business case
  • D. Project statement of work
Show Suggested Answer Hide Answer
Suggested Answer: BCD 🗳️
The Develop Project Charter process documents the formal authorization of a project or a phase. It also documents initial requirements that satisfy the stakeholder's needs and expectations. It is used to validate the decisions made during the previous iteration of the Develop Project Charter process. The various inputs of this process are as follows:
✑ Project statement of work
✑ Business case
✑ Contract
✑ Enterprise environmental factors
✑ Organizational process assets
✑ The output of the Develop project Charter process is as follows:
✑ Project charter
Incorrect Answers:
A: Procurement document is the input of the Identify Stakeholders process.

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Currently there are no comments in this discussion, be the first to comment!
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...