exam questions

Exam PMI-SP All Questions

View all questions & answers for the PMI-SP exam

Exam PMI-SP topic 2 question 46 discussion

Actual exam question from PMI's PMI-SP
Question #: 46
Topic #: 2
[All PMI-SP Questions]

John is the project manager for his organization. Management has asked John to fast track his project in order to reach a particular date for the project completion.
When John fast tracks the project what project management component must be updated to reflect this decision? Choose the best answer.

  • A. Organizational process assets
  • B. Cost management plan
  • C. Resource calendars
  • D. Risk register
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️
Fast tracking allows phases of the project to overlap and increases risk for the project. When new risks are introduced into the project they should be recorded in the risk register. Risk register is a document that contains the results of the qualitative risk analysis, quantitative risk analysis, and risk response planning.
Description, category, cause, probability of occurring, impact on objectives, proposed responses, owner, and the current status of all identified risks are put in the risk register.
Incorrect Answers:
A: Organizational process assets are updated as a result of updating the risk register when you consider that the risk register will become part of the organizational process assets. However, this is not the best answer for this question.
B: The costs do not change because of the new fast tracking requirement.
C: Resource calendars show the availability of project resources.

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Currently there are no comments in this discussion, be the first to comment!
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...