Joseph works as the project manager of the NHQ Project. He has created the project network diagram as shown in the figure:

Based on the network diagram, find out which path is the critical path for this project?

  • A. ABEHJ
  • B. ABDIJ
  • C. ABDHJ
  • D. ACFIJ
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️
The critical path is the path with the longest duration to complete the project. It has no float and shows the earliest completion date and the latest completion date for the project. In this example, path ACFIJ takes 27 days and is the critical path.
ACFIJ= A(4)+C(8)+F(4)+I(7)+J(4)= 27
A critical path is the sequence of project activities, which add up to the longest overall duration. This determines the shortest time possible to complete the project.
Any delay of an activity on the critical path directly impacts the planned project completion date (i.e. there is no float on the critical path). A project can have several, parallel, near critical paths. An additional parallel path through the network with the total durations shorter than the critical path is called a sub-critical or non-critical path. These results allow managers to prioritize activities for the effective management of project completion, and to shorten the planned critical path of a project by pruning critical path activities, by "fast tracking" (i.e., performing more activities in parallel), and/or by "crashing the critical path" (i.e., shortening the durations of critical path activities by adding resources).
Incorrect Answers:
A: ABEHJ takes only 22 days to complete.
ABEHJ= A(4)+B(5)+E(2)+H(7)+J(4)= 22
B: ABDIJ takes 21 days to complete.
ABDIJ= A(4)+B(5)+D(1)+I(7)+J(4)= 21
C: ABDHJ takes 21 days to complete.
ABDHJ= A(4)+B(5)+D(1)+H(7)+J(4)= 21

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Currently there are no comments in this discussion, be the first to comment!
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...