Suggested Answer:A🗳️
Lag time is positive time that requires the successor activity to wait for a defined amount of time, such as three days, before it can begin. Lag time does not change the task relationship, but requires a "waiting time" before the starting of the activity can begin. A lag time is a delay between the predecessor and the successor tasks. Sometimes it may be needed to schedule a delay between the predecessor and the successor tasks. For example, if two coats of paint are required to paint a car, then the final coat should be applied only when the first coat dries. This delay is known as the lag time. The lag time is entered as a positive value. The lag time can be entered as a duration or as a percentage of the predecessor's task duration. It is entered on the Predecessor tab in the Task Information dialog box. Incorrect Answers: B: Management reserve is a pool of time allotted for unscheduled changes and events that affect the project duration. C: Lead time actually brings activities closer together and causes them, in some cases, to overlap. D: Float is a natural event that is discovered through the forward pass when using the critical path method. Float cannot be arbitrarily added as lag.
Currently there are no comments in this discussion, be the first to comment!
This section is not available anymore. Please use the main Exam Page.PMI-SP Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Comments