exam questions

Exam PMI-SP All Questions

View all questions & answers for the PMI-SP exam

Exam PMI-SP topic 2 question 127 discussion

Actual exam question from PMI's PMI-SP
Question #: 127
Topic #: 2
[All PMI-SP Questions]

If you are the project manager of the BNQ Project and you add "waiting time" between two activities, then what have you added in the project?

  • A. You have added lag time to the project activities.
  • B. You have added management reserve to the project activities.
  • C. You have added lead time to the project activities.
  • D. You have added float to the project activities.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️
Lag time is positive time that requires the successor activity to wait for a defined amount of time, such as three days, before it can begin. Lag time does not change the task relationship, but requires a "waiting time" before the starting of the activity can begin. A lag time is a delay between the predecessor and the successor tasks. Sometimes it may be needed to schedule a delay between the predecessor and the successor tasks. For example, if two coats of paint are required to paint a car, then the final coat should be applied only when the first coat dries. This delay is known as the lag time. The lag time is entered as a positive value. The lag time can be entered as a duration or as a percentage of the predecessor's task duration. It is entered on the Predecessor tab in the Task
Information dialog box.
Incorrect Answers:
B: Management reserve is a pool of time allotted for unscheduled changes and events that affect the project duration.
C: Lead time actually brings activities closer together and causes them, in some cases, to overlap.
D: Float is a natural event that is discovered through the forward pass when using the critical path method. Float cannot be arbitrarily added as lag.

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Currently there are no comments in this discussion, be the first to comment!
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...