exam questions

Exam CAPM All Questions

View all questions & answers for the CAPM exam

Exam CAPM topic 1 question 295 discussion

Actual exam question from PMI's CAPM
Question #: 295
Topic #: 1
[All CAPM Questions]

A project team is working on relocating offices to another building and providing new furniture. The new furniture was purchased from an international vendor. The price was negotiated in a foreign currency, and due to changes in the exchange rate, the cost has increased by 10%. There is no contingency in the project budget.

What should the project manager do?

  • A. Escalate this issue to the procurement team.
  • B. Escalate this issue to the project sponsor.
  • C. Escalate this issue to the chief financial officer (CFO).
  • D. Escalate this issue to the project management office (PMO).
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
JesseChou_123
1 month, 2 weeks ago
Selected Answer: B
Why the other options are incorrect: A. Escalate to the procurement team: ❌ The procurement team might help negotiate terms or manage vendor relations, but they don’t control the project budget or authorize additional spending. C. Escalate to the CFO: ❌ The CFO oversees organizational finances, but would typically not be involved in day-to-day project budget decisions—unless the project sponsor involves them. D. Escalate to the PMO: ❌ The PMO provides governance and methodology support, but it’s not responsible for approving additional project funding.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...