Exam CAPM topic 1 question 296 discussion

Actual exam question from PMI's CAPM
Question #: 296
Topic #: 1
[All CAPM Questions]

A project manager is assigned to a new project with a defined scope. The project requires advanced planning at the start of the project.

Which approach should the project manager select for the project?

  • A. Adaptive
  • B. Predictive
  • C. Hybrid
  • D. Kanban
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
JesseChou_123
1 month, 1 week ago
Selected Answer: B
Key phrases "advanced planning at the start of the project" = Predictive (Waterfall)
upvoted 1 times
...
JesseChou_123
1 month, 3 weeks ago
Selected Answer: B
Why the other options are incorrect: A. Adaptive: ❌ Used when requirements are evolving or not well defined. It emphasizes iterative development and flexibility — not appropriate here. C. Hybrid: ❌ Combines predictive and adaptive methods. Useful when some parts are predictable and others need flexibility — not needed if the entire scope is already well defined. D. Kanban: ❌ A visual workflow management method often used in adaptive or agile environments. It supports continuous delivery but is not designed for projects with extensive upfront planning.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...