Exam CAPM topic 1 question 297 discussion

Actual exam question from PMI's CAPM
Question #: 297
Topic #: 1
[All CAPM Questions]

A project team working on an automobile manufacturing project is detailing the parts needed for a car door design. The door is composed of several parts that have to be developed in sequence, as the frame is needed before other parts can be designed and built.

What activity is the team involved in?

  • A. Developing a stakeholder engagement plan
  • B. Developing a communications management plan
  • C. Creating a work breakdown structure (WBS)
  • D. Identifying risks and issues in the project
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
JesseChou_123
1 month, 2 weeks ago
Selected Answer: C
Why the other options are incorrect: A. Developing a stakeholder engagement plan: ❌ This deals with identifying and managing stakeholder expectations—not with breaking down technical work. B. Developing a communications management plan: ❌ This focuses on how project information will be shared, not on technical breakdowns of product components. D. Identifying risks and issues in the project: ❌ This focuses on potential uncertainties—not the task of defining and sequencing work.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...