Exam CAPM topic 1 question 319 discussion

Actual exam question from PMI's CAPM
Question #: 319
Topic #: 1
[All CAPM Questions]

An adaptive team schedules 20 story points in the upcoming sprint. Historically, the team completes 25 story points on average per sprint. Each sprint is two weeks, and there is one day of float.

What is the likelihood the team will complete all 20 story points in the upcoming sprint?

  • A. 50-75%
  • B. 25-50%
  • C. 75-100%
  • D. 0-25%
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
JesseChou_123
1 month, 1 week ago
Selected Answer: C
This is a question of predictability and probability based on historical velocity. The team scheduled 20 story points. The team historically completes 25 story points per sprint. Each sprint is 2 weeks, and there’s 1 day of float (additional time for flexibility). Why 75–100%? The team consistently delivers more (25) than what they’ve committed to now (20). 20 is within the team's historical capacity, so the team is underloading, likely to ensure quality and manage risk. The 1 day of float increases the buffer, further improving the chances of meeting the commitment. So, the likelihood of completing 20 story points is high—well within the team’s historical performance, hence the probability is in the 75–100% range.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...