The handoff of the first version of a software application to the operational team has taken a month longer than anticipated. How could this extended transition time have been avoided?
A.
If the transition process was agreed upon during the build
B.
If the end-user documentation was more thorough
C.
If the operation team members were trained externally
D.
If the operations manager was invited to all sprint reviews
Why the other options are less effective:
B. If the end-user documentation was more thorough
❌ While helpful, documentation alone doesn’t solve process misalignment or readiness gaps in the transition.
C. If the operation team members were trained externally
❌ External training may help in skill development, but doesn’t guarantee alignment with the project-specific handoff process.
D. If the operations manager was invited to all sprint reviews
❌ Sprint reviews help with visibility, but don’t substitute for structured transition planning agreed upon during the build.
upvoted 1 times
...
This section is not available anymore. Please use the main Exam Page.CAPM Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
JesseChou_123
1Â month, 1Â week ago