Question #: 332
Topic #: 1
[All CAPM Questions]

Which of the following is part of the project sponsor's responsibility?

  • A. Tracking the business value
  • B. Auditing the business value
  • C. Monitoring the business value
  • D. Advocating the business value
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
JesseChou_123
1 month, 1 week ago
Selected Answer: D
Why the other options are incorrect: A. Tracking the business value ❌ Typically done by the project manager or business analyst as part of benefits realization tracking. B. Auditing the business value ❌ Performed by independent audit teams or governance bodies—not the sponsor. C. Monitoring the business value ❌ While the sponsor is aware of value delivery, ongoing monitoring is generally the responsibility of the project manager or PMO.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...