Question #: 342
Topic #: 1
[All CAPM Questions]

A project team is brainstorming about the best methods and practices to adopt for an upcoming project. What is the project team trying to follow?

  • A. Programs
  • B. Portfolios
  • C. Standards
  • D. Concepts
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
JesseChou_123
1 month, 1 week ago
Selected Answer: C
Why the other options are incorrect: A. ❌ A program is a group of related projects managed together—not a set of methods or practices. B. ❌ A portfolio is a collection of projects and programs aligned to strategic goals—not a set of standards or practices. D. ❌ Concepts are broad ideas or theories—not necessarily structured or widely adopted best practices.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...