The project is in the execution phase and the project manager is expected to produce all required project artifacts. Which three are relevant artifacts produced during project execution? (Choose three.)
A. Work performance reports – ✅
These are outputs of project execution, compiled from raw work performance data and information, and used to inform stakeholders of project status.
B. Issue log – ✅
During execution, new issues are identified and tracked. The issue log is created and maintained as part of ongoing execution.
C. Business case – ❌
This is created before project initiation to justify the project. It is not produced or revised during execution.
D. Scope management plan – ❌
This is part of the project management plan, developed during planning, not execution.
E. Change requests – ✅
During execution, change requests commonly arise due to unexpected conditions, issues, or stakeholder needs.
upvoted 1 times
...
This section is not available anymore. Please use the main Exam Page.CAPM Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
JesseChou_123
1 month, 1 week ago