Exam CAPM topic 1 question 365 discussion

Actual exam question from PMI's CAPM
Question #: 365
Topic #: 1
[All CAPM Questions]

The project is in the execution phase and the project manager is expected to produce all required project artifacts. Which three are relevant artifacts produced during project execution? (Choose three.)

  • A. Work performance reports
  • B. Issue log
  • C. Business case
  • D. Scope management plan
  • E. Change requests
Show Suggested Answer Hide Answer
Suggested Answer: ABE 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
JesseChou_123
1 month, 1 week ago
Selected Answer: ABE
A. Work performance reports – ✅ These are outputs of project execution, compiled from raw work performance data and information, and used to inform stakeholders of project status. B. Issue log – ✅ During execution, new issues are identified and tracked. The issue log is created and maintained as part of ongoing execution. C. Business case – ❌ This is created before project initiation to justify the project. It is not produced or revised during execution. D. Scope management plan – ❌ This is part of the project management plan, developed during planning, not execution. E. Change requests – ✅ During execution, change requests commonly arise due to unexpected conditions, issues, or stakeholder needs.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...