Question #: 25
Topic #: 1
[All PMI-ACP Questions]

Midway through a sprint, a team member discovers that the product design fails to adhere to the organization's enterprise architecture standards. Since this required escalation to the architecture team for further analysis and resolution, the team was unable to deliver its sprint goal and the sprint was cancelled.
What should the team have done to avoid this?

  • A. Escalated the issue to management
  • B. Ensured the early engagement of key stakeholders
  • C. Provided feedback to the architecture team to change the enterprise architecture standards
  • D. Raised an exception for non-adherence to the enterprise architecture standards for this product
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Alex1904
Highly Voted 3 years, 8 months ago
Just out of curiosity, who provides these answers, and why are so many of them wrong. It seems it is done on purpose to confuse people and make mistakes during the exam...
upvoted 16 times
...
zvasanth3
Highly Voted 4 years, 3 months ago
MY CHOICE IS Ensured the early engagement of key stakeholders
upvoted 15 times
zvasanth1
4 years, 3 months ago
The answer D applicable only if the architecture team processes takes more time than the sprint duration
upvoted 2 times
...
...
Nervys
Most Recent 11 months ago
B for sure
upvoted 1 times
...
Imrangoshi
1 year, 2 months ago
Selected Answer: B
B is the Correct Answer
upvoted 1 times
...
Petrevski
1 year, 8 months ago
B - the only early option to be conducted. After that the issue is already risen and you cannot avoid it. Also: A - what can do the management? C - why change the standards, the product design has to be improved. D - typical technical debt
upvoted 1 times
...
InvisibleBeing
1 year, 10 months ago
Selected Answer: B
B is correct. B is the only option that would have avoided the issue. The remaining options are about what to do after the issue was identified and not related with avoiding the issue.
upvoted 1 times
...
7029
1 year, 10 months ago
Selected Answer: B
B is the most to avoid from begining.
upvoted 1 times
...
richck102
2 years, 4 months ago
B sure
upvoted 1 times
...
JackNguyenvn
2 years, 8 months ago
B is correct
upvoted 1 times
...
hobou
3 years, 1 month ago
it's b for me
upvoted 1 times
...
adelshenouda
3 years, 3 months ago
B, the best choice
upvoted 1 times
...
Abbey2
3 years, 4 months ago
Should they give all correct answers, some exam takers will not bother to study to ace the exams...so much pressure will eventually be on the dump industry to close down! imagine 100% of test takers scoring above proficient in all areas!
upvoted 1 times
...
tsangckl
4 years, 1 month ago
It should be B.
upvoted 5 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...