exam questions

Exam PMI-ACP All Questions

View all questions & answers for the PMI-ACP exam

Exam PMI-ACP topic 1 question 51 discussion

Actual exam question from PMI's PMI-ACP
Question #: 51
Topic #: 1
[All PMI-ACP Questions]

Why should a project team reduce the work in progress?

  • A. It indicates poor project quality
  • B. It represents team member's utilization
  • C. It represents unrealized value
  • D. It shows that the project is behind schedule
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
chlaithem
10 months, 1 week ago
Selected Answer: C
A. Poor project quality: While high WIP can sometimes be a symptom of poor quality, it's not always the case. Reducing WIP can improve quality, but it is just one aspect of overall quality improvement. B. Team member utilization: WIP doesn't directly represent team member utilization. Even with low WIP, team members can be fully engaged in completing other tasks related to the project. D. Project behind schedule: WIP can contribute to being behind schedule, but it's not the sole reason. Reducing WIP can improve speed and delivery, but other factors like scope, dependencies, and communication also play a role.
upvoted 1 times
...
Urchman
1 year, 7 months ago
i WOULD HAVE CHOSEN A
upvoted 1 times
...
Petrevski
1 year, 7 months ago
Selected Answer: C
C = correct
upvoted 2 times
...
Smokeyofficiial
1 year, 8 months ago
Option C. In Agile, reducing the work in progress (WIP) is a key principle known as "Limiting Work in Progress" (WIP). The goal is to focus on completing a smaller number of tasks to increase the team's capacity to deliver high-quality work. By reducing WIP, the team can better manage their workload and ensure that they are delivering value to the customer. Additionally, it allows the team to identify and address any issues that arise during the project in a more timely manner. Therefore, reducing WIP represents unrealized value that can be delivered to the customer if the team focuses on completing a smaller number of tasks.
upvoted 1 times
...
Holly2023
1 year, 9 months ago
Selected Answer: C
C - user stories value is unrealized until it is completed. In Lean software development, this is partially completed work and considered waste.
upvoted 1 times
...
InvisibleBeing
1 year, 10 months ago
Selected Answer: D
I would go with D. Unrealized Value has nothing to do with WIP. Please do your research and you will understand that WIP and unrealized value are totally unrelated.
upvoted 1 times
...
minwang
2 years, 2 months ago
Selected Answer: C
I believe C is the right answer
upvoted 2 times
...
richck102
2 years, 3 months ago
C sure
upvoted 1 times
...
Edgarrt
2 years, 7 months ago
Selected Answer: C
WIP limits improve throughput and reduce the amount of work "nearly done", by forcing the team to focus on a smaller set of tasks
upvoted 2 times
...
thuha1704
2 years, 8 months ago
I choose C
upvoted 1 times
...
Alaaradwan
3 years, 4 months ago
D the correct answer
upvoted 1 times
...
zvasanth3
4 years, 3 months ago
if every developer works on their own story means all the stories in inventory mode(unrealized value). if all the developers works on the single story at least this one story will reach the customer
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...