A new product owner shares the product vision during the team launch event. The team asks for clarification on the product roadmap and its high-level features. What should the product owner do?
A.
Determine the required tasks for implementing the high-level features
B.
Identify the detailed design for the high-level features
C.
Prioritize the product backlog for the upcoming release
D.
Estimate the user stories in the iteration backlog
C - Correct - Clarification of the product roadmap should be done by prioritizing the backlog. (sequencing of deliverables over time).
From PMI’s Agile Practice Guide, Page 52:
“Product owners (or a product owner value team that includes the product manager and all relevant product owners for that area of the product,) might produce a product roadmap to show the anticipated sequence of deliverables over time.”
I selected A because all 4 seem incorrect, and A is less incorrect, I believe. C is irrelevant to the question, but it is a true statement overall... Actually the only true statement about PO is C, but again, irrelevant to the question.
Why not A ? think about it, the product roadmap is about the high-level plan and the team askes for clarification, so here we should think about the role of PO according to the request/question being asked by the team. The question doesnt ask about the next step in order to select C !Do you agree with me ?!
Correct. C is about prioritizing backlog, which in any case PO would do. But to identify high level feature, a new PO should check on stories/tasks associated with it.
A. Determine the required tasks for implementing the high-level features - team is. not going to implement the high-level features - it will be part of iteration planning - wrong
B. Identify the detailed design for the high-level features
C. Prioritize the product backlog for the upcoming release - it is team launch event, they are not going to proritze - it will happen in release planning or iteration planning - wrong
D. Estimate the user stories in the iteration backlog - it is team launch event, they are not going to Estimate - it will happen in iteration. wrong
But product owner is not responsible for identifying detailed design. It is the responsibility of the development team. In my opinion, the answer should be C
upvoted 8 times
...
...
This section is not available anymore. Please use the main Exam Page.PMI-ACP Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
GPena
Highly Voted 4 years, 6 months agoHTTPS
Highly Voted 3 years, 11 months agojosephsafiran
Most Recent 6 months, 3 weeks agoImrangoshi
1 year, 8 months agoabhi517
2 years, 1 month agocutri89
2 years, 1 month agoPetrevski
2 years, 1 month agoInvisibleBeing
2 years, 3 months ago7029
2 years, 4 months agoChikhalsouk
2 years, 6 months agogogiap
2 years, 7 months agorichck102
2 years, 10 months agothuha1704
3 years, 2 months agosnow5
4 years, 6 months agoAzurance
3 years, 10 months agotsangckl
4 years, 7 months agozvasanth3
4 years, 9 months agonavingthomas
4 years, 7 months ago