An agile practitioner notices that team members are disengaged. As a result, the team's velocity has decreased.
What should the agile practitioner do to get the team back on track?

  • A. Escalate the issue to the project sponsor
  • B. Remove stories to increase velocity
  • C. Hold a standup to address the issue
  • D. Facilitate a team retrospective
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Petrevski
6 months, 3 weeks ago
Selected Answer: D
D = correct
upvoted 2 times
...
Minhha3
7 months, 2 weeks ago
Vote D
upvoted 1 times
...
InvisibleBeing
9 months, 4 weeks ago
Selected Answer: D
D is correct. Daily standup is not the right event to discuss such issues. Daily standup is for inspect and adapt to achieve the sprint goal.
upvoted 1 times
...
richck102
1 year, 4 months ago
D sure
upvoted 1 times
...
thuha1704
1 year, 8 months ago
D is correct
upvoted 2 times
...
Deer
2 years, 2 months ago
My answer is D, Talk in retro
upvoted 1 times
...
aws_guru1
2 years, 2 months ago
D is definitely the answer
upvoted 1 times
...
HTTPS
2 years, 6 months ago
D - Correct From PMI’s Agile Practice Guide, Page 51: “However, the team does not need iterations in order to retrospect. Team members may decide to retrospect at these key times: When the team completes a release or ships something. It does not have to be a monumental increment. It can be any release, no matter how small. When more than a few weeks have passed since the previous retrospective. When the team appears to be stuck and completed work is not flowing through the team. When the team reaches any other milestone.”
upvoted 3 times
...
abrieftesttolearn2020
2 years, 12 months ago
Answer is D
upvoted 2 times
...
snow5
2 years, 12 months ago
Reto is dedicated for team performance improvement, thus D is the right answer
upvoted 2 times
...
GPena
3 years ago
D sure
upvoted 2 times
...
gnc123
3 years, 3 months ago
C is fine but why not D?
upvoted 1 times
tsangckl
3 years, 1 month ago
team retrospective is once per sprint. It can't be bring the velocity back on track immediately.
upvoted 3 times
srv3
2 years, 11 months ago
Team member can summon retro anytime during iteration and any number of times during iteration. Retro is hold when team / team member identifies opportunity for improvement. Retro as sprint event obligated to be once during the sprint, but not limited to.
upvoted 3 times
...
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...