The product owner of an agile project is frustrated because the team is unable to deliver as many features as expected. The product owner asks the team to reduce test-automation levels, since the quality assurance team will test the product at project completion. The product owner expects that more features will be delivered in each iteration using this approach.
What should the agile practitioner do?

  • A. Ask the opinion of key stakeholders and the client to ensure the correct approach is being used
  • B. Work with the team to use this approach, and request a quality assurance iteration after every three iterations
  • C. Propose to completely eliminate test automation, since this is a quality assurance function
  • D. Suggest merging the quality assurance and delivery teams to enhance each iteration's test-automation levels and redundancy
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
zvasanth1
Highly Voted 4 years, 8 months ago
Agile testing suggests that development and testing go side by side answer would be D
upvoted 13 times
...
zayn_1983
Most Recent 10 months, 2 weeks ago
Selected Answer: A
It’s crucial to involve key stakeholders and possibly the client in decisions that could impact product quality and delivery.
upvoted 1 times
...
Imrangoshi
1 year, 8 months ago
Selected Answer: D
D is the Correct Answer
upvoted 1 times
...
Raksim
2 years ago
C. Test will still be done by the team, only the automated ones will be done by the QA team. The idea is to eliminate wasting time by doing it twice.
upvoted 1 times
...
Raksim
2 years ago
Before making any decisions, the Agile practitioner should ask the opinion of key stakeholders and the client to ensure that the correct approach is being used. Stakeholders and the client have a vested interest in the quality of the product and can provide valuable feedback on the proposed approach. Based on the feedback received, the Agile practitioner can work with the team and product owner to find a solution that ensures the product's quality while delivering value to the customer in each iteration.
upvoted 4 times
Doltish
2 years ago
I also think A is the best action for this scenario
upvoted 3 times
...
...
cutri89
2 years, 1 month ago
Selected Answer: D
i thik this
upvoted 1 times
...
Petrevski
2 years, 1 month ago
Selected Answer: D
D - correct
upvoted 1 times
...
InvisibleBeing
2 years, 3 months ago
Selected Answer: D
D is correct. Finding defects as early as possible is the ultimate goal to reduce cost of change at a later stage.
upvoted 1 times
...
Eli8
2 years, 9 months ago
I go for (C) becauuse it will meet agile principle 2:....Agile processes harness change for the customer's competitive advantage.
upvoted 1 times
...
cozyhead
2 years, 9 months ago
Selected Answer: D
Answer is D
upvoted 1 times
...
richck102
2 years, 10 months ago
D sure
upvoted 1 times
...
JackNguyenvn
3 years, 1 month ago
D is correct
upvoted 1 times
...
tpkhoa
3 years, 6 months ago
D is the correct one for me. The team should be cross-functional team. If we don't do Automation test like PO suggested, the cost for fixing the bug at the end of project will very high. it will become a kind of waterfall model.
upvoted 4 times
...
GPena
4 years, 6 months ago
D should be the answer
upvoted 4 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...