During its first sprint, a new scrum team realizes that it has insufficient team members with test automation skills to efficiently complete its stories. What should the team do?
A.
Cross-train some members in the automation framework to broaden their capacity with that skill
B.
Ask the product owner to add team members to boost this particular skill set
C.
Send a member to automation framework training when funds are available
D.
Avoid using test automation by swarming on the testing tasks and using manual testing
I don't agree. It says insuficient (meaning not enough) not "nobody". Also I am not sure whether a PO has the authority to add members to a team or make that decision. In my experience he/she doesn't but I might be wrong. In any case, I believe A is the correct answer.
I agree. It also mentions "effectively" meaning they're completing the stories, just ineffectively. Hence, there is someone capable of performing this task.
Option A.
Agile teams are encouraged to be self-organizing and collaborative, and team members are expected to be multi-skilled and cross-functional. By cross-training some members in automation, the team can improve their overall capacity to complete testing tasks efficiently and effectively. This approach also supports knowledge sharing and team building within the group. If cross-training is not feasible or sufficient, the team can explore other options such as recruiting or requesting additional team members with the required skill set.
But it says "during its first sprint" meaning that there is no time for training as the question ends with "to complete its stories". Therefore B suits better, to complete the stories DURING the sprint.
Let's make clear some question:
- What do we have spike US for?
- If we have another insufficient skills, example CI/CD, Deployment, Database query,... will we need to add how many members to do it?
A for me.
Encourage team members to become generalizing specialists in
order to reduce team size and bottlenecks, and to create a high performing cross-functional team. https://www.pmi.org/-/media/pmi/documents/public/pdf/certifications/agile-certified-exam-outline.pdf?v=f48bd86f-bf3f-4b9c-830b-b91ce3b1cfd7&sc_lang_temp=en
A. Cross-train some members in the automation framework to broaden their capacity with that skill-- nobody has knowledge so we cannot cross train
B. Ask the product owner to add team members to boost this particular skill set
C. Send a member to automation framework training when funds are available
- dont know when the fund will be available
D. Avoid using test automation by swarming on the testing tasks and using manual testing
- test automation part of agile
B is a right answer
Let's make clear some question:
- What do we have spike US for?
- If we have another insufficient skills, example CI/CD, Deployment, Database query,... will we need to add how many members to do it?
insufficient , it's not mentioned that there is no one with that skill
upvoted 2 times
...
...
This section is not available anymore. Please use the main Exam Page.PMI-ACP Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
diligentstudent
Highly Voted 3 years, 1 month agoxero180sx
3 years, 1 month agoPetrevski
Most Recent 6 months, 3 weeks agoMinhha3
6 months, 3 weeks agoSmokeyofficiial
7 months, 2 weeks agoInvisibleBeing
9 months, 1 week agoSerakuska
10 months, 3 weeks agominwang
1 year, 1 month agorichck102
1 year, 3 months agoJackNguyenvn
1 year, 7 months agotpkhoa
2 years agoHTTPS
2 years, 5 months agoSARS
2 years, 8 months agotsangckl
3 years agoqwertypassword
3 years agonavingthomas
3 years agozvasanth1
3 years, 2 months agoHTTPS
2 years, 5 months agotpkhoa
2 years agoAlb65
1 year, 2 months ago