Exam PMI-ACP topic 1 question 68 discussion

Actual exam question from PMI's PMI-ACP
Question #: 68
Topic #: 1
[All PMI-ACP Questions]

More details for a story are required before the upcoming sprint planning meeting.
What should the scrum master do?

  • A. Email the product owner requesting detailed story specifications and wait for a response
  • B. Gather the details from the team members before sprint planning
  • C. Schedule a story grooming session with the product owner before sprint planning
  • D. Conduct a planning poker session with the team
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
snow5
Highly Voted 2 years, 11 months ago
C is the answer, Grooming (or refinement) is a meeting of the Scrum team in which the product backlog items are discussed and the next sprint planning is prepared. Product grooming is critical in product management because it means keeping the backlog up to date and getting backlog items ready for upcoming sprints
upvoted 10 times
...
aws_guru1
Highly Voted 2 years, 1 month ago
Who is providing these answers from Exam Topics? This is not a difficult question but the answer is still wrong. C is the correct answer
upvoted 8 times
...
Petrevski
Most Recent 6 months, 3 weeks ago
Selected Answer: C
C = correct
upvoted 1 times
...
Minhha3
6 months, 3 weeks ago
Vote C
upvoted 1 times
...
Smokeyofficiial
7 months, 2 weeks ago
Option C. In Agile, a story grooming session is a collaborative meeting between the development team and the product owner to review and refine product backlog items (PBIs) to ensure they are well-defined and understood by the team. It is also known as backlog refinement. If more details are required for a story before the upcoming sprint planning meeting, the scrum master should schedule a story grooming session with the product owner to discuss and refine the story. During this session, the team and the product owner can discuss the story details, ask questions, clarify any ambiguities, and break it down into smaller tasks or user stories, if necessary.
upvoted 1 times
...
InvisibleBeing
9 months, 1 week ago
Selected Answer: C
C it is.
upvoted 1 times
...
cozyhead
1 year, 2 months ago
Selected Answer: C
C for sure
upvoted 1 times
...
richck102
1 year, 3 months ago
C sure
upvoted 1 times
...
JackNguyenvn
1 year, 7 months ago
C is correct
upvoted 1 times
...
mikyngure
3 years ago
C should be right answer
upvoted 5 times
...
Polar_Bear
3 years, 1 month ago
C. The team doesn't know or own stories, the PO does. If the PO later says the team's description was wrong, what happens then?
upvoted 5 times
...
zvasanth1
3 years, 2 months ago
The answer should be B, right?
upvoted 1 times
zvasanth1
3 years, 2 months ago
sorry C
upvoted 5 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago