The team is in the middle of an iteration and there is an urgent request for a small change to be introduced to the committed scope. Unless this change is accepted, there is no value to the customers during this iteration.
What must the agile practitioner do?
zvasanth1
Highly Voted 3 years, 2 months agomaryl
Highly Voted 3 years, 2 months agoPetrevski
Most Recent 6 months, 4 weeks agoPetrevski
7 months agoMinhha3
7 months, 2 weeks agoSmokeyofficiial
8 months agoInvisibleBeing
10 months agoInvisibleBeing
10 months agoInvisibleBeing
10 months agominwang
1 year, 2 months agocozyhead
1 year, 3 months agonguyenducttk5
1 year, 3 months agorichck102
1 year, 4 months agoJackNguyenvn
1 year, 7 months agoiratsi
2 years, 5 months agonavingthomas
2 years, 9 months agosnow5
3 years agoGPena
3 years ago