exam questions

Exam PMI-ACP All Questions

View all questions & answers for the PMI-ACP exam

Exam PMI-ACP topic 1 question 88 discussion

Actual exam question from PMI's PMI-ACP
Question #: 88
Topic #: 1
[All PMI-ACP Questions]

The team is in the middle of an iteration and there is an urgent request for a small change to be introduced to the committed scope. Unless this change is accepted, there is no value to the customers during this iteration.
What must the agile practitioner do?

  • A. Add the new change request as a new user story in the product backlog for the upcoming iteration
  • B. Evaluate the impact of the change request and let the team and product owner decide and re-prioritize based on value
  • C. Recommend cancelling the current iteration and plan the change request into the next iteration
  • D. Recommend that the product owner add this change request as a user story to the backlog for the current iteration
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
zvasanth1
Highly Voted 3 years, 2 months ago
B makes sense
upvoted 11 times
...
maryl
Highly Voted 3 years, 2 months ago
agreed. I question many of the answers in the higher numbers.
upvoted 7 times
...
Petrevski
Most Recent 6 months, 4 weeks ago
Selected Answer: B
B = correct
upvoted 1 times
...
Petrevski
7 months ago
Selected Answer: B
B = correct
upvoted 1 times
...
Minhha3
7 months, 2 weeks ago
Vote B
upvoted 1 times
...
Smokeyofficiial
8 months ago
Option B. In Agile, change is expected and change requests can arise anytime. However, it is important to evaluate the impact of the change request and determine the value it brings to the customer. The team and product owner should work together to decide whether to accept the change request, re-prioritize the backlog and make adjustments accordingly. This ensures that the team is focused on delivering value to the customer and the product backlog is aligned with the priorities of the stakeholders.
upvoted 1 times
...
InvisibleBeing
10 months ago
Selected Answer: B
I am changing my answer from D to B. It seems B is the correct answer.
upvoted 1 times
...
InvisibleBeing
10 months ago
Selected Answer: D
I am going with D. Sorry to say but "B" cannot be the answer. Please look at the first part of option B: "EVALUATE THE CHANGE REQUEST". The Agile coach does not evaluate the impact alone by himself, impact analysis is always done with the entire team (including dev team and PO). The dev team and PO are the only one to understand the impact to the sprint goal. Second, in option B it says to reprioritize based on value. Why waste time reprioritizing something that you already know is important and without which the sprint delivers no value.
upvoted 2 times
InvisibleBeing
10 months ago
I am changing my answer from D to B.
upvoted 1 times
...
...
minwang
1 year, 2 months ago
C is the right answer
upvoted 1 times
...
cozyhead
1 year, 3 months ago
Correct answer is B
upvoted 1 times
...
nguyenducttk5
1 year, 3 months ago
Selected Answer: B
B is correct
upvoted 1 times
...
richck102
1 year, 4 months ago
B sure
upvoted 1 times
...
JackNguyenvn
1 year, 7 months ago
B is correct
upvoted 1 times
...
iratsi
2 years, 5 months ago
How come it is A? Agile practitioner cannot add user stories. I think B is correct.
upvoted 2 times
...
navingthomas
2 years, 9 months ago
If the required change is so important that the results of the Sprint would be worthless without it, then the Sprint should be terminated. If not, then the change is incorporated into a later Sprint. In this case the answer will be "C" Ref : http://blog.scrumstudy.com/how-are-changes-to-a-sprint-managed-in-scrum/
upvoted 3 times
...
snow5
3 years ago
B make more sense, however, we should think also about C since the question says without such change there is no value to customers in the current iteration ?
upvoted 3 times
...
GPena
3 years ago
B make sense to the answer
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...