Exam PMI-ACP topic 1 question 62 discussion

Actual exam question from PMI's PMI-ACP
Question #: 62
Topic #: 1
[All PMI-ACP Questions]

A development team and product owner disagrees on a user story in the product backlog.
What should the agile practitioner do?

  • A. Have the development team follow the product owner's direction
  • B. Openly challenge the product owner in the effort to poke holes in their approach
  • C. Facilitate a conversation about the user story between the development team and the product owner
  • D. Serve as a nonpartisan evaluator of each option, and provide direction to the development team and product owner
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
zvasanth1
Highly Voted 3 years, 2 months ago
my choice is C
upvoted 11 times
...
Petrevski
Most Recent 7 months ago
C = correct
upvoted 1 times
...
Smokeyofficiial
7 months, 2 weeks ago
Option C. Facilitate a conversation about the user story between the development team and the product owner. In Agile Framework, collaboration and communication are key values. In this situation, the agile practitioner should facilitate a conversation between the development team and the product owner to understand each other's perspectives and find a solution that satisfies both parties. It is important to note that the agile practitioner should not take sides but rather act as a facilitator to ensure a healthy and productive discussion.
upvoted 1 times
...
InvisibleBeing
9 months, 1 week ago
Selected Answer: C
C it is.
upvoted 1 times
...
minwang
1 year, 1 month ago
C for sure
upvoted 1 times
...
cozyhead
1 year, 2 months ago
my answer is C
upvoted 1 times
...
richck102
1 year, 3 months ago
i vote C
upvoted 1 times
...
JackNguyenvn
1 year, 7 months ago
The answer is C
upvoted 2 times
...
srv3
2 years, 11 months ago
Scrum Master is facilitator and coach. He/She can't neither give direction regarding the tasks nor evaluate options. C seems to be the best answer.
upvoted 2 times
...
snow5
2 years, 11 months ago
I think C
upvoted 3 times
...
GPena
2 years, 12 months ago
Communication bewtween part is important. It is D
upvoted 1 times
GPena
2 years, 11 months ago
Sorry, C
upvoted 2 times
...
...
tsangckl
3 years ago
My answer is C
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago