An agile team adds a user story related to architecture improvement in the current iteration. The product owner is not pleased, but the team says it must be added to the current iteration to minimize risk.
What should the product owner do?
A.
Allow the team to add the improvement to the current iteration after considering the risk.
B.
Review project integration management to determine which iteration should have the improvement added.
C.
Analyze the project schedule to determine which iteration should have the improvement added.
D.
Request the team to add it to the next iteration as the risk must be properly assessed.
Why the other options are incorrect:
B. Review project integration management
This is a concept from traditional (predictive) project management, not agile. Agile doesn’t manage work through integration documents in this way.
C. Analyze the project schedule
Agile uses product backlogs and velocity, not detailed project schedules. This is a predictive approach, not aligned with agile principles.
D. Request the team to add it to the next iteration
This delays addressing a known risk, which may increase technical debt or instability — not ideal if the team has flagged it as urgent.
Shouldnot add a story in current iteration. Needs to go through sprint planning and backlog prioritization process.
upvoted 1 times
...
This section is not available anymore. Please use the main Exam Page.CAPM Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
JesseChou_123
1 month ago8a6d137
3 months, 3 weeks ago