exam questions

Exam CAPM All Questions

View all questions & answers for the CAPM exam

Exam CAPM topic 1 question 462 discussion

Actual exam question from PMI's CAPM
Question #: 462
Topic #: 1
[All CAPM Questions]

An agile team adds a user story related to architecture improvement in the current iteration. The product owner is not pleased, but the team says it must be added to the current iteration to minimize risk.

What should the product owner do?

  • A. Allow the team to add the improvement to the current iteration after considering the risk.
  • B. Review project integration management to determine which iteration should have the improvement added.
  • C. Analyze the project schedule to determine which iteration should have the improvement added.
  • D. Request the team to add it to the next iteration as the risk must be properly assessed.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
8a6d137
2 weeks ago
Selected Answer: D
Shouldnot add a story in current iteration. Needs to go through sprint planning and backlog prioritization process.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago