Exam CAPM topic 1 question 403 discussion

Actual exam question from PMI's CAPM
Question #: 403
Topic #: 1
[All CAPM Questions]

What tool can be used to track how involved and interested stakeholders are in a project?

  • A. Stakeholder assessment matrix
  • B. Stakeholder communications plan
  • C. Stakeholder register
  • D. Stakeholder meetings
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
8a6d137
1 week, 6 days ago
Selected Answer: A
engagement levels can be shown in a Stakeholders Engagement Assessment Matrix.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.