A project manager is creating a project charter to provide a direct link between the project and the organization's strategic objectives. What must be considered when creating this document?
A.
High-level requirements and the project team
B.
Key stakeholder list and contingency reserve
C.
Detailed milestone schedule and project objectives
D.
Project purpose and high-level project description
Why not the others?
A. High-level requirements and the project team
→ High-level requirements may be included, but the project team is not typically identified yet at this early stage.
B. Key stakeholder list and contingency reserve
→ Stakeholders may be included, but contingency reserves are part of cost planning, not the charter.
C. Detailed milestone schedule and project objectives
→ Detailed milestones are developed during planning, not in the charter. The charter only includes summary milestones.
upvoted 1 times
...
This section is not available anymore. Please use the main Exam Page.CAPM Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
JesseChou_123
2 weeks, 2 days ago